Frequently Asked Questions

Frequently Asked Questions from residents about Darwin Green

How do I report an issue?

See the dedicated page.

How do I keep up-to-date with local events?

When do facilities open?

Estimates are usually provided by Barratt, the developer, during the North West and West Cambridge Community Forums. Last updated in June 2026.

Library
Estimated opening time: late 2026 or early 2027
NHS Centre
Unknown. Fit-out contract work expected to start in summer 2026.
Retail units on the Plaza
Sale of the retail units estimated for the end of 2026.
Sports Pavilion
Transfer to City Council estimated for Autumn 2026.
Allotments (Parcel BDW2)
Transfer to City Council estimated for Autumn 2026.
Connection path between Darwin Green and Franklin Gardens
Unknown. The work on BDW4 must progress further for the path to open.
Livies Kinder Café
Unknown. The project received planning permission in July 2025. Check out the Livies’ website for the latest information.
Potential primary school in Darwin Green 1
Unknown. Pending a decision from the Department of Education about what to do with the site.
Secondary school in Darwin Green 2
After 2028, no timeline at the moment

When is the work expected to be completed?

Phase 1 (parcel BDW1), local centre
Complete
Phase 2 (parcel BDW2)
In progress, to be completed in 2026
Phase 3 (parcel BDW4)
In progress, to be completed in 2027
Phase 4 (parcel BDW3)
Due to start in summer 2026

The site should be complete by the end of 2031.

Where do I park my car in Darwin Green?

See the dedicated page.

My phone has no network connection in Darwin Green, what can I do?

Residents have reported that EE provides the best coverage in the area.

Contact for using the sports pitches?

If you run a team and would like information or to show interest in booking the sports pitches in Darwin Green, you should send your questions to ParksandRecreation@cambridge.gov.uk.